TSat-3

TSat-3A and TSat-3B, the fourth Tethered Satellite mission, launching together in early 2027.

TSat-3 is in development. This page will grow as the teams complete their design reviews.

TSat-3 is the fourth Tethered Satellite mission. Like TSat-2, it is split into two independent satellites, TSat-3A and TSat-3B, which will launch together. Both teams completed Mission Concept Reviews in early fall 2026, and Preliminary Design Reviews were due October 23, 2026. The goal is to finish both satellites by the end of the fall 2026 semester and launch in January 2027.

TSat-3A: attitude control

TSat-3A's main goal is a stabilization system: reaction wheels that hold the satellite's rotation about its vertical (Z) axis so the camera view stays steady while it hangs from the balloon.

Mission goals:

  • Stabilization with reaction-wheel attitude control (main focus)

  • Live telemetry over LoRa

  • High-resolution video recorded on board

  • Parachute deployment

Progress as of October 2026:

  • The team got the reaction wheels left over from the club's Knight Satellite project spinning again, then ran into motor driver problems and is now evaluating stepper motors and controllers.

  • The structure is a hybrid of 3D-printed parts and aluminum bars.

  • Telemetry tests compare ESP-NOW (ESP32) with LoRa. The team is also looking at an encoder on the balloon connection to measure rotation on the line, and at a pilot or drogue parachute.

TSat-3B: parafoil return to launch site

TSat-3B's main goal is to steer itself back to the launch site under a parafoil after it is released.

Mission goals:

  • Parafoil recovery that returns to the launch site (main focus)

  • Live telemetry

The concept is a 1U payload hanging under a parafoil, with automated steering and manual commands as a backup. It carries GPS, a power distribution board, and a large battery, with two ESP32s for control. A normal parachute is on standby in case the parafoil isn't ready. A test parafoil of about 1 m² is being used for early testing. Because the satellite needs open space to land, the team is looking for a launch site other than the UCF Arboretum used by earlier missions.

Building on TSat-2

  • TSat-2A originally planned a guided parafoil but dropped it in September 2025 because it wouldn't fit a one-semester schedule. TSat-3B picks that goal back up.

  • The TSat-2A lessons learned apply to both teams: test separation and parachute deployment end to end with the final hardware, freeze the design early, and verify critical actions physically rather than relying on a software acknowledgement.

  • TSat-2B's live telemetry code is a starting point for both teams' telemetry. The TSat-2A and TSat-2B timelines show where the last mission's schedule slipped.

Timeline so far

Planned
Actual

Kickoff

September 2026

September 8, 2026

Mission Concept Reviews

End of the week of September 28

Early October 2026

Preliminary Design Reviews

October 23, 2026

Due October 23, 2026

Completion

December 2026

Launch

January 2027

  • September 8, 2026: first meeting. Ideas and parts lists were brainstormed.

  • September 9, 2026: so many people joined that the project split into two teams, TSat-3A and TSat-3B. Members can work on either.

  • September 10, 2026: mission schedule, inventory, and concept documents shared.

  • September 2026: 3A compared motors, wheel materials, cameras, and parachutes; 3B researched parafoils and set a mass limit of 2 kg.

  • October 6, 2026: 3A got the old KS-1 reaction wheels working. 3B presented its MCR overview.

  • Week of October 13, 2026: 3A hit motor driver problems and started looking at stepper motors. 3B dropped the Raspberry Pi Pico in favor of two ESP32s.

  • Week of October 20, 2026: early test components ordered for 3A; 3B's test parafoil expected.