> For the complete documentation index, see [llms.txt](https://wiki.kscucf.org/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://wiki.kscucf.org/projects/tethered-satellite/t-sat-2/t-sat-2-mission-a/timeline.md).

# Timeline

How TSat-2A went from kickoff in September 2025 to its flight on March 28, 2026, including how the design changed.

This page records how TSat-2A actually went, from kickoff to launch, so future teams can plan their own schedules.

## At a glance

|                              | Planned          | Actual                           |
| ---------------------------- | ---------------- | -------------------------------- |
| Kickoff                      | Early fall 2025  | First meeting September 16, 2025 |
| Mission Concept Review (MCR) | September 2025   | Submitted September 24, 2025     |
| Parts ordered                | October 2025     | October 30, 2025                 |
| Launch                       | End of fall 2025 | March 28, 2026                   |
| Total                        | One semester     | About six and a half months      |

TSat-2 was the first mission run with defined goals, deliverables, and deadlines and with less direct help from the Board. Its program goals were to give project leads leadership experience, give new members start-to-finish project experience in one semester, and let the Projects Committee practice managing projects.

## Fall 2025: concept and design

* **August 17, 2025:** planning started for TSat-2, with two sister projects (2A and 2B) and separate leads.
* **September 16, 2025:** first TSat-2A meeting. The first concept was a 2U satellite with a **guided parafoil**, steered by a servo-driven reel, plus cameras and altitude sensing. Four subteams were set up: communications, mechanical, guided parafoil, and separation system. The Projects Committee shared a draft mission timeline the same day.
* **September 18, 2025:** layout settled: cameras and a three-layer PCB stack in the lower 1U, the parafoil control system in the upper 1U, and a spring-loaded parafoil release.
* **September 23, 2025:** the spring-loaded release was dropped in favor of a **top panel separation system**: four servos with hook-and-ring latches release the 2U body from a top panel that stays on the balloon line.
* **September 24, 2025:** MCR submitted to the Board.
* **September 26, 2025:** after MCR feedback, the guided parafoil was dropped because it would not fit a one-semester schedule for newer members. The mission focused on the separation system and a parachute.
* **September 30, 2025:** parts list finalized and sent to the treasurer. CAD of the housing and PCB started. Software planned a five-state flight program (calibration, preflight, ascent, free fall, landing), with separation at about 400 ft or on command.
* **October 2025:** PCB schematic in EasyEDA. The MMA8451 accelerometer was removed from the design.
* **October 30, 2025:** orders placed for both TSat-2 teams. The chosen battery was a rocket-igniter LiPo with its protection circuit removed, so it was replaced with protected cells, and the servo got its own battery and boost converter.
* **November 16, 2025:** first PCB layout finished. Review found long, winding traces and no layer changes, so the board was moved into KiCad in the club's GitHub organization on November 25.
* **December 2025:** the semester ended without a launch.

## Spring 2026: build and launch

* **January 13, 2026:** meetings resumed, with an extra electrical meeting on Fridays.
* **January 2026:** CAD updates, including resizing holes for heat-set inserts.
* **February 25, 2026:** launch date set for March 28, pending approvals. Flight Readiness Reviews were planned for both teams.
* **March 24–27, 2026:** daily meetings and field testing before launch. A servo panel was replaced shortly before launch, which left little time for end-to-end testing.
* **March 27, 2026:** dress rehearsal at the launch site.
* **March 28, 2026:** TSat-2A flew second, after TSat-2B. The separation command was received but needed intervention, and the parachute did not deploy. See [Flight Results](https://wiki.kscucf.org/projects/tethered-satellite/t-sat-2/t-sat-2-mission-a/flight-results.md).

## What slipped and why

* **Scope:** the guided parafoil was in the original plan, and dropping it two weeks in kept the mission achievable.
* **PCB design** took most of the fall, including a move from EasyEDA to KiCad after review. With winter break, this pushed the launch into the next semester.
* **Late changes** in the last week left the final configuration untested, which likely contributed to the parachute failure.

## Advice for future teams

* Get the PCB reviewed by an experienced member early. Schedule fabrication so boards arrive before winter break.
* Check battery datasheets for protection circuits and current ratings before ordering.
* Freeze the design at least a week before launch and test the final configuration end to end.