> For the complete documentation index, see [llms.txt](https://wiki.kscucf.org/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://wiki.kscucf.org/projects/tethered-satellite/t-sat-1/timeline.md). Agents can also search and read this documentation through its [MCP server](https://wiki.kscucf.org/~gitbook/mcp).

# Timeline

How TSat-1 went from kickoff in February 2025 to its flight on June 21, 2025.

This page records how TSat-1 actually went, from kickoff to launch, so future teams can plan their own schedules.

## At a glance

|         | Planned              | Actual                       |
| ------- | -------------------- | ---------------------------- |
| Kickoff | Start of spring 2025 | February 7, 2025             |
| Launch  | End of spring 2025   | June 21, 2025                |
| Total   | One semester         | About four and a half months |

TSat-1 was a refinement of TSat-0 rather than a new design, which is why it moved much faster.

## Timeline

* **December 2024:** the Board opened applications for a TSat-1 lead.
* **February 7, 2025:** first TSat-1 meeting. Goals: fix TSat-0's early parachute deployment, improve usability of the mechanical parts, and smooth launch day operations.
* **February 2025:** a burn wire PCB was considered to replace the protoboard unit. Higher frame rate cameras were deferred to TSat-2.
* **March 28, 2025:** testing started in the engineering atrium.
* **April 2025:** I2C errors (NACKs) from the sensors were traced with a logic analyzer and fixed by slowing the bus to 50 kHz. See [Software](https://wiki.kscucf.org/projects/tethered-satellite/t-sat-1/software.md).
* **May 19, 2025:** replacement parts ordered (cameras, ESP32 devkits, and an accelerometer board).
* **June 10, 2025:** image transfers brought down to about 30 seconds by raising the SPI clock to 16 MHz; any faster and the SD card failed.
* **June 16–18, 2025:** integrated tests: elevator tests, then drop tests from a parking garage into a tablecloth held by members. The burn wire ground unit worked intermittently. The fishing line turned out to be too thick to burn through, so it was replaced with thinner 8 lb test line (0.011 in).
* **June 17, 2025:** UCF approved the launch.
* **June 19, 2025:** 3D-printed parts replaced the metal carabiners and rings used on TSat-0.
* **June 21, 2025:** TSat-1 flew from the UCF Arboretum. The burn wire released it and the parachute deployed at the correct altitude. The satellite landed in a tree and was recovered the next day after a thunderstorm, then dried out and checked. See [Flight Results](https://wiki.kscucf.org/projects/tethered-satellite/t-sat-1/flight-results.md).
* **June–August 2025:** mechanical and flight documentation written for the wiki.

## What worked

* Reusing a flown design let the team focus on a short list of fixes.
* Testing the whole system in drop tests a week before launch caught the fishing line problem in time.

## Advice for future teams

* Test the burn wire with the exact line you will fly.
* Plan for recovery from trees: bring a way to reach high branches, or pick a launch spot with fewer trees downwind.
* Write documentation right after launch while everyone remembers the details.