# Timeline

How TSat-0 went from kickoff in fall 2023 to its first flight in January 2025, including the delays and what caused them.

This page records how TSat-0 actually went, from kickoff to launch, so future teams can plan their own schedules.

## At a glance

|                  | Planned                          | Actual                                                          |
| ---------------- | -------------------------------- | --------------------------------------------------------------- |
| Kickoff          | Start of fall 2023               | First meeting early October 2023, after room reservation delays |
| First drop tests | After spring break 2024          | November 2024                                                   |
| Launch           | Within the first semester or two | January 20, 2025, after three scrubbed launch dates             |
| Total            | One to two semesters             | About three and a half semesters                                |

## Fall 2023: getting started

* **September 2023:** project announced; finding a meeting time and room took most of the month.
* **October 2023:** first meetings. The team split into mechanical, avionics, and software. Avionics picked the core parts (ESP32, MMA8451 accelerometer, BMP3xx barometer, Seeeduino XIAO, and RFM radio modules for the burn wire).
* **November 2023:** mechanical started the parachute canister. An early concern was the parachute catching on the release pin, which became a test requirement.

## Spring 2024: design

* **January–February 2024:** the meeting time changed three times because of room reservation problems, which cost several weeks.
* **February 26, 2024:** an Arducam camera was working with the ESP32.
* **March 2024:** work started on the flight software and the avionics PCB. The PCB was ordered on March 24 without a servo connector; the team worked around it with a JST-XH connector.
* **April 2024:** estimated mass reached about 400 g, which set the balloon size. Side panel CAD lagged because the mechanical lead had little free time.

**Issue:** the plan to start drop tests after spring break slipped by about seven months.

## Summer 2024: software

* **June 2024:** saving one camera image took about 8 seconds, which could delay parachute deployment if the altitude threshold was crossed mid-save. Using FreeRTOS tasks was proposed as the fix.
* **June–August 2024:** software continued; the servo panel waited while the mechanical lead moved.

## Fall 2024: integration and testing

* **November 7, 2024:** the burn wire's TIP120 transistor wasn't switching fully on from the XIAO, so it couldn't drive enough current. A new transistor circuit was designed and tested.
* **November 8, 2024:** the first fully assembled TSat-0 was put together and software testing began.
* **November 13–15, 2024:** final mass 408 g. The satellite was demonstrated to the club's advisors.
* **Mid-November 2024:** in drop tests the parachute often failed to deploy, even with simplified software. Causes found: the remove-before-flight limit switch, a low battery, and a binding servo linkage (fixed by changing the linkage and buying a stronger servo). Accelerometer free-fall detection also failed when the satellite was spinning.
* **November 22, 2024:** the November 23 launch was scrubbed because the helium delivery slipped to the following week.
* **December 3–5, 2024:** the flight software was reworked around FreeRTOS. Image writes were starving the idle task, and the camera and SD card were corrupting each other's SPI traffic. A mutex around the SPI bus and a separate logging task fixed it, giving full-quality images about every 15 seconds alongside consistent telemetry.
* **December 6, 2024:** the December 8 launch was scrubbed when university approval paperwork was rejected the Friday before launch, including a request for a certificate of liability insurance.

## January 2025: launch

* **January 13, 2025:** UCF approved a launch on January 19.
* **January 18, 2025:** launch moved one day because of lightning risk.
* **January 20, 2025:** TSat-0 flew twice from the UCF Arboretum. The parachute deployed early on both flights, triggered by the accelerometer; the barometer alone would have worked. The burn wire release worked on the second flight. See [Flight Results](https://wiki.kscucf.org/projects/tethered-satellite/t-sat-0/flight-results.md).
* **Late January 2025:** flight data was charted for the GBM and the wiki write-up began. TSat-1 kicked off two weeks later.

## What slipped and why

* **Room reservations** cost weeks at the start of two semesters. Book rooms before the semester starts.
* **Single points of failure in people.** CAD and software each depended on one busy person, so progress stopped when they were unavailable.
* **Late integration.** The satellite wasn't fully assembled until about two weeks before the first planned launch, so problems that only show up in drop tests were found late.
* **Launch logistics** (helium delivery, university paperwork, weather) caused all three scrubs. None were technical.

## Advice for future teams

* Start launch approvals and gas orders at least a month before the launch date, and confirm with UCF exactly what paperwork they need.
* Build a working "Frankenstein" version early, even if it's ugly, and drop test it as soon as possible.
* Buy spares of everything, especially batteries, servos, and SD cards.
* Choose a launch window in advance and decide the weather rules before launch day.