KAOS-2
KAOS-2, the third KAOS high-altitude balloon mission, targeting launch in February 2027.
KAOS-2 is the third mission of the KAOS program: a CubeSat-class payload flown on a high-altitude balloon. It is mostly a revised version of KAOS-1, using similar technology and a similar payload, including APRS tracking. Launch is targeted for February 2027.
Goals
Fix the thermal problems that caused KAOS-1's electronics to overheat and power cycle early in its flight (see the KAOS-1 lessons learned).
Fly a custom-designed APRS board with a new antenna.
Add power telemetry.
Carry a LoRa module as a backup tracker.
Status (October 2026)
Thermal: the team is building a thermal chamber. Thermal testing will decide the redesign of the payload box.
Structure: new CAD is in progress.
Communications: the team is still troubleshooting the off-the-shelf LightAPRS 2 module, which led to the goal of building a custom APRS board.
Cameras: a fisheye camera and a standard camera each work on their own, but not yet together.
Recovery: a 5 ft parachute has been chosen.
Mission patch: in design.
Timeline so far
Kickoff
May 2026
May 13, 2026
Launch
July 18, 2026
Moved four times; now targeted for February 2027
September 2025: ideas for KAOS-2 collected while KAOS-1 results were reviewed.
May 13, 2026: KAOS-2 kicked off with a new project lead, aiming for a mid-July launch to show KAOS can be flown reliably and with redundancy.
Summer 2026: the team built on the KAOS-1 flight software and worked on an APRS and camera stack. On July 20 the antenna was tested at Cocoa Beach.
July 17, 2026: the July 18 launch was postponed to August 15 (August 22 as backup) to fix open issues.
August 19, 2026: launch pushed to around September for more testing.
September 2026: a new project lead took over for the fall, targeting October 17 or November 7.
October 13, 2026: thermal testing supplies arrived.
October 20, 2026: project goals were reset: launch in February 2027 with a custom APRS board and antenna, power telemetry, and a LoRa backup tracker (confirmed October 23).
Lesson so far: the July date was set before the team knew how much of KAOS-1's hardware needed rework, especially the thermal design and the APRS tracker. Setting the date after a design review would have avoided repeated slips.