KAOS-2

KAOS-2, the third KAOS high-altitude balloon mission, targeting launch in February 2027.

KAOS-2 is in development. Flight results will be added after launch.

KAOS-2 is the third mission of the KAOS program: a CubeSat-class payload flown on a high-altitude balloon. It is mostly a revised version of KAOS-1, using similar technology and a similar payload, including APRS tracking. Launch is targeted for February 2027.

Goals

  • Fix the thermal problems that caused KAOS-1's electronics to overheat and power cycle early in its flight (see the KAOS-1 lessons learned).

  • Fly a custom-designed APRS board with a new antenna.

  • Add power telemetry.

  • Carry a LoRa module as a backup tracker.

Status (October 2026)

  • Thermal: the team is building a thermal chamber. Thermal testing will decide the redesign of the payload box.

  • Structure: new CAD is in progress.

  • Communications: the team is still troubleshooting the off-the-shelf LightAPRS 2 module, which led to the goal of building a custom APRS board.

  • Cameras: a fisheye camera and a standard camera each work on their own, but not yet together.

  • Recovery: a 5 ft parachute has been chosen.

  • Mission patch: in design.

Timeline so far

Planned
Actual

Kickoff

May 2026

May 13, 2026

Launch

July 18, 2026

Moved four times; now targeted for February 2027

  • September 2025: ideas for KAOS-2 collected while KAOS-1 results were reviewed.

  • May 13, 2026: KAOS-2 kicked off with a new project lead, aiming for a mid-July launch to show KAOS can be flown reliably and with redundancy.

  • Summer 2026: the team built on the KAOS-1 flight software and worked on an APRS and camera stack. On July 20 the antenna was tested at Cocoa Beach.

  • July 17, 2026: the July 18 launch was postponed to August 15 (August 22 as backup) to fix open issues.

  • August 19, 2026: launch pushed to around September for more testing.

  • September 2026: a new project lead took over for the fall, targeting October 17 or November 7.

  • October 13, 2026: thermal testing supplies arrived.

  • October 20, 2026: project goals were reset: launch in February 2027 with a custom APRS board and antenna, power telemetry, and a LoRa backup tracker (confirmed October 23).

Lesson so far: the July date was set before the team knew how much of KAOS-1's hardware needed rework, especially the thermal design and the APRS tracker. Setting the date after a design review would have avoided repeated slips.