> For the complete documentation index, see [llms.txt](https://wiki.kscucf.org/llms.txt). Markdown versions of documentation pages are available by appending `.md` to page URLs; this page is available as [Markdown](https://wiki.kscucf.org/projects/knights-air-observation-satellite/kaos-1/timeline.md).

# Timeline

How KAOS-1 went from replanning in June 2022 to its flight on August 30, 2025, including what caused three years of development.

This page records how KAOS-1 actually went, from replanning after KAOS-0 to launch, so future teams can plan their own schedules.

## At a glance

|               | Planned                                                                                                                                     | Actual                |
| ------------- | ------------------------------------------------------------------------------------------------------------------------------------------- | --------------------- |
| Start         | June 2022                                                                                                                                   | June 2022             |
| PCBs designed | 2023                                                                                                                                        | March 2024            |
| Launch        | No date at first. Later targets: summer 2024 (hoped for in fall 2023), end of spring 2024, December 2024, February 2025, and August 4, 2025 | August 30, 2025       |
| Total         | Not set at the start                                                                                                                        | Just over three years |

## 2022: replanning

* **June 2022:** after KAOS-0, the team planned KAOS-1 as a return to the high-altitude balloon: KAOS-0's sensors plus GPS and a camera, most likely in a 4U frame so the camera would fit. A requirements document and BOM were started.
* **July 2022:** the project scope and system requirements were mapped out in Innoslate.
* **Fall 2022:** meetings resumed. The sensors and GPS arrived on October 12.
* **October 29, 2022:** at a conference, the team learned how hard recovery can be from Florida (balloons can drift into the ocean) and got contacts and prediction tools for balloon flights. Tracking options were compared, and APRS was chosen because it uses the free amateur radio network.
* **December 2, 2022:** the first laser-cut plywood prototype of the housing. The first APRS module the team had picked was discontinued.

## 2023: research and design

* **February 2023:** the main microcontroller changed from an ATmega to an ESP32, which is smaller and still uses Arduino code. Camera temperature limits led the team to insulate the box instead of cutting windows in it. The LightAPRS tracker was chosen but was out of stock. A club GitHub organization and the KAOS-1 repository were created.
* **March 2023:** a Florida Space Grant Consortium grant request was prepared with the club's advisor.
* **April 2023:** the team found that some GPS receivers stop working above 18 km (COCOM limits), so the receiver had to be chosen carefully.
* **September–October 2023:** the housing was redesigned with dovetail joints. Plywood samples were freezer-tested and sealed to check for warping. The first data logging test code was written, and a power budget was started.
* **November 2023:** the lead who had run KAOS since 2022 stepped down at the end of the semester.

**Issue:** most of 2023 was research, with small turnouts and leads busy with senior design. There was no firm launch date to work toward.

## 2024: hardware

* **February 2024:** a new lead took over. On February 24 the team toured the National Weather Service office in Ruskin to watch a weather balloon launch.
* **March 1, 2024:** thermal testing with dry ice in a cooler.
* **March 2024:** after a frustrating weekend with the ESP32's built-in camera library, the team moved to Arducam Mega cameras. APRS packets were received and decoded with an SDR. The four-board PCB stack (Power, Sensor, Primary, Communications) was designed in EAGLE in about three weeks and ordered.
* **April–May 2024:** balloon and parachute ordered. Sourcing lifting gas took weeks: university labs and the weather service couldn't supply it, so the team turned to commercial gas suppliers.

**Issue:** the goal of launching by the end of spring 2024 slipped. The boards were assembled, but integration and software weren't finished.

* **September 2024:** new goal: hardware done by October 25 (before the SmallSat Education Conference), software in November, and a December launch from out of state for a safer landing zone. One candidate site in North Carolina was dropped after hurricane damage.
* **October 2024:** flatsat test software written. Gas quotes compared.
* **November 2024:** KAOS work paused so the team could finish TSat-0.

## 2025: integration and launch

* **January 2025:** work resumed, targeting a launch in February.
* **February 13, 2025:** the TSat-0 flight software, which had flown the month before, was copied into the KAOS-1 repository as the starting point for KAOS-1's flight software. The parachute servo code was removed. See [Software](https://wiki.kscucf.org/projects/knights-air-observation-satellite/kaos-1/software.md#heritage-from-tsat).
* **February 2025:** clearance problems in the board stack. A voltage regulator broke and was repaired. The SD card worked intermittently.
* **March 6, 2025:** the updated housing was laser cut and assembly began. Replacement regulators arrived on March 10.
* **April 2025:** remaining software tasks (thermistor reading, buzzer, pin definitions) were handed to new members.
* **Late May–June 2025:** launch readiness discussions.
* **July 16, 2025:** the LightAPRS's onboard 3.3 V regulator was found dead, so it was powered through its 3.3 V output pin instead.
* **July 23, 2025:** a flat antenna on the top of the housing gave a GPS lock in about 3 minutes.
* **July 2025:** launch planned for August 4 from a central Florida site, coordinated with the FAA.
* **July 29, 2025:** launch moved to August 30 to allow more testing and software work, and so new members could see a launch.
* **August 4 and 25, 2025:** APRS range tests near Kennedy Space Center didn't reach the APRS network reliably, and the tracker rebooted at times.
* **August 26, 2025:** a broken PCB sled rail needed replacing four days before launch.
* **August 28–29, 2025:** launch site chosen by running flight predictions for four sites; Econ River Wilderness Area gave the best landing area.
* **August 30, 2025:** KAOS-1 launched just after 10:00 am, burst at about 111,000 ft at 11:23 am, landed around 12:10 pm, and was recovered about 10 miles away. See [Launch Day](https://wiki.kscucf.org/projects/knights-air-observation-satellite/kaos-1/launch-day.md) and [Post Flight Results](https://wiki.kscucf.org/projects/knights-air-observation-satellite/kaos-1/post-flight-results.md).
* **September 3, 2025:** the flight video was published.
* **October 2026:** a post-flight analysis found that the SPOT tracker's altitude wraps every 32,768 ft. Correcting for it against the onboard pressure log settled the peak altitude, which had been estimated at about 120,000 ft.

## What slipped and why

* **No firm launch date for the first year and a half.** Work expanded to fill the time.
* **Leadership changes** in late 2023 and turnover each semester meant knowledge had to be rebuilt.
* **Sharing people with other projects.** KAOS paused for TSat-0 in late 2024.
* **Launch logistics** (lifting gas, launch sites, FAA coordination) took months and were started late.

## What worked

* **Reusing flown software.** Starting from the TSat-0 flight software instead of writing new code meant KAOS-1 flew with a state machine and task structure that had already been debugged on a real flight.

## Advice for future teams

* Set a launch date early and plan backwards from it.
* Start lifting gas, launch site, and FAA planning at least two months before launch.
* Test the tracker's range in realistic conditions well before launch, and carry a backup tracker.
* Log pressure from launch so there's an altitude record that doesn't depend on the tracker.
* Keep documentation current so a new lead can pick up where the last one left off.
* When reusing code from another project, check for fixes made to the original after you copied it.