# Timeline

How work on the Engineering and Physics ground stations has gone since 2024, including what has blocked progress.

This page records how the ground station projects have actually gone, so future teams can plan their own schedules.

## At a glance

| Station                                                                                              | Started     | Status (October 2026)                                                 | Main blocker                                |
| ---------------------------------------------------------------------------------------------------- | ----------- | --------------------------------------------------------------------- | ------------------------------------------- |
| [Engineering](https://wiki.kscucf.org/projects/ground-stations/engineering-ground-station.md) (ENG1) | August 2024 | Radio, rotator, and controller work; antennas and coax need replacing | Repairs at the top of a 30 ft rooftop tower |
| [Physics](https://wiki.kscucf.org/projects/ground-stations/physics-ground-station.md) (PSB)          | April 2025  | Commissioning: tracking works, first satellite receptions attempted   | Roof access and approvals                   |

## Engineering Ground Station (ENG1)

* **August 30, 2024:** KSC met with the UCF Amateur Radio Club (ARC\@UCF), which owns the station. Its Yaesu G-5500 rotator had no way to be controlled from a computer, so KSC took on a Raspberry Pi Pico controller as a side project and training exercise.
* **September–November 2024:** schematic drafted, Pico development environment set up, and controller firmware started in the [g5500-pico-controller](https://github.com/UCF-Knights-Satellite-Club/g5500-pico-controller) repository.
* **November 2024–January 2025:** paused while the team finished TSat-0.
* **February 2025:** the firmware worked from a terminal but not through Hamlib. On March 8, Hamlib's rotator daemon worked reliably.
* **March 12, 2025:** the G-5500 pinout and voltage ranges were checked on a new cable. The controller uses relays, so speed control (PWM) is not practical.
* **March 26, 2025:** the motor control circuit didn't work. Controller work stopped here.
* **September 2025:** work restarted in the ARC shack. Both 70 cm antennas were found broken; the 2 m antenna worked. A Yaesu GS-232 computer interface left over from UCF's Q-PACE mission was found at the Physics station and used on the G-5500 instead, which made the custom controller unnecessary.
* **October–November 2025:** the antennas needed replacing and the tower needed an inspection before anyone could work on it.
* **January–February 2026:** problems with the coax or antennas continued, and something on the tower broke while the rotator was in use. ARC and KSC plan to replace the antennas and coax, which is costly and difficult on a 30 ft tower. The KSC student lead for the station stepped down in February.

## Physics Ground Station (PSB)

* **April 9, 2025:** first visit to the station in PSB 461. Members need lab safety training for access.
* **September 2025:** weekly meetings started. On September 23 the team got Hamlib and rigctl working with the transceiver and set it up with a static IP for a direct Ethernet connection to the PC.
* **October 2025:** a rotator calibration procedure was drafted from the manufacturer's documentation. Calibration needed roof access, which needed separate roof safety training.
* **November 2025:** meetings paused while waiting for roof access.
* **January–February 2026:** Florida Space Grant Consortium funding paid for a new 2 m antenna (M2 2M7X), chosen with help from ARC. Roof training was held on February 23.
* **March 2026:** a new Ground Stations lead took over. Installing the antenna required a safety harness and department permission.
* **May 2026:** still waiting on roof permissions; documentation for the station was written up.
* **June 2026:** parts lists started for Student Government funding requests.
* **August 20, 2026:** the new 2 m antenna was installed.
* **September 2026:** a roof leak delayed work. On September 23 Linux was installed on one station computer after backing it up. On September 29 the tower was raised and the antennas were found mounted too low in elevation.
* **October 14, 2026:** antennas remounted for full elevation range; rotator zeroed on magnetic north; tracking from GPredict and Hamlib set up; ground beacons received with the SDR. A first satellite attempt heard nothing.
* **October 20, 2026:** the coax wrapped around the rotator and pulled the connector off the 2 m antenna; it needs a new connector.
* **October 21, 2026:** Debian installed on Troi with rotator control verified. A first attempt at FO-29 briefly heard a distorted voice signal.
* **October 2026:** the rotator controller's stored position repeatedly stopped matching where the rotator was actually pointing, and it was reset several times by eye from the ground. Still under investigation.

## What slowed things down

* **Roof access.** For the Physics station, about 16 months passed between the first visit and installing the new antenna, mostly waiting for training, safety equipment, and permission.
* **Old equipment.** Both stations have aging antennas and coax. Expect repairs before anything works.
* **Tower access at ENG1.** Every repair at the top of the Engineering station's tower needs a climb, which is expensive and hazardous. The Physics station's retractable tower avoids this.
* **Shared people.** The same members worked on TSat-0 and KAOS-1, so ground station work paused when those had launches.

## Advice for future teams

* Start roof training and permission requests at the beginning of the semester, and keep a list of trained people.
* Leave enough coax slack and check the cable path through the rotator's full range of motion.
* Log every rotator reset or calibration, with readings before and after and how the direction was checked.
* Get an amateur radio license early; you need one to transmit.